| 1. | If the room is on a concrete slab:
a. The floor must be as level as possible.
b. The concrete floor must be treated with waterproof sealer. |
| 2. | Walls need to be constructed of 2x4 or 2x6 studs. All corners must be squared using the 3-4-5
method to square walls. (See figure 1 below)
(Figure 1)
|
| 3. | Walls will need 2x6 nailers between studs, below top plate and above sill plate to anchor racking. (This step not needed if using plywood sheeting. See # 13) |
|
| |

Find out more about our worldwide factory direct installations.

Have more installation questions? Contact our installation manager to get your answers.
|
|

Print PDF File |